The Overpass at Vintage Oaks' Front Door Has a Schematic and County Support. It Doesn't Have a Start Date Yet.

October 22, 2026

Head west from FM 3159 on State Highway 46 toward Bulverde and the road changes partway there. Past Bentwood Drive, crews have spent close to four years turning a two-lane highway into six lanes with raised medians. Between Bentwood Drive and the Smithson Valley Road intersection, the stretch Vintage Oaks residents use most, the highway is still the older two-lane layout.

That gap was planned. The overpass meant for the SH 46 and FM 3159 intersection has land, environmental clearance, a schematic and a county resolution behind it. What it doesn't have yet is funding or a construction date, and the regional planning documents suggest it will be a while.

The six-lane road stops at Bentwood Drive

The work underway now is TxDOT's widening of SH 46 from just west of Farhills Drive to just east of Bentwood Drive. According to TxDOT's project page, it takes the road from two lanes with two-way traffic to six lanes with raised medians and a center left-turn lane.

The Herald-Zeitung reported that the project costs $59 million, that Webber LLC is the contractor, and that construction started in late 2022. When that article ran, the project was about half done and TxDOT expected to finish in spring 2026. TxDOT's project page now gives an estimated completion of Winter 2026. It describes nighttime paving for the final road surface and topsoil and hydromulch work, with traffic signals and roadside elements still to be finished. So the date has slipped from spring to winter, and as of this week the official word is still an estimate.

TxDOT's older study page for the whole corridor, from Bulverde Road to FM 3159, which it also calls Smithson Valley Road, once listed "Late 2022" as the construction start for SH 46 from Farhills Drive to Smithson Valley Road. The page calls that timeline preliminary and subject to change. When construction did start that year, the contract ran only to Bentwood Drive. The last piece, the one that reaches Vintage Oaks, was split off to be built later.

What the county voted for in January

On January 8, 2026, Comal County Commissioners Court approved Resolution #2026-01 supporting an overpass at SH 46 and FM 3159. Commissioner Doug Leecock made the motion, Commissioner Scott Haag seconded it, and the vote was unanimous.

County Engineer Robert Boyd's presentation, summarized in the court's official minutes, laid out where things stand:

"TxDOT has already purchased the right-of-way along the north side of 46. Environmental clearance has been made on this project. TxDOT asked for a Resolution back in October to confirm Comal County supported the project."

The minutes call the design "a major interchange." They also note that the $39 million construction cost "would come from MPO or State funds, not necessarily from the County," and that TxDOT wanted the county's support on record "to make sure if they move forward with getting funding for the project, we are supportive as well."

That wording explains what the resolution does. It doesn't fund anything. It gives TxDOT a local endorsement to bring along when it competes for money. My Canyon Lake's coverage the same day described the project as a standalone overpass. It reported that construction on the state-funded $39 million project is expected to begin "sometime in the next five to 10 years" and that TxDOT already owns the right of way.

The same estimate, three years apart

This was the second time the court voted to back this overpass. The Herald-Zeitung covered an earlier resolution, passed on Thursday, Dec. 8. The county's meeting archive shows the court met that day in 2022. In that article, Boyd said the section from Bentwood Drive to FM 3159, including the overpass, was expected to begin construction "in the next five to 10 years." The paper also reported $39 million in state funding, completed right-of-way purchases and environmental clearance.

Compare the two meetings. In December 2022 the start was five to ten years away. In January 2026 the start was still described as five to ten years away. The land, the clearance and the cost estimate were the same both times. TxDOT asked for a fresh vote anyway, which fits a project still waiting in line for funding rather than one about to start.

Where 2033 comes from

The regional planning documents give an actual year. The Alamo Area Metropolitan Planning Organization's draft Transportation Improvement Program for fiscal 2025 to 2028, reviewed in April 2024, lists the SH 46 segment from Bentwood Drive to FM 3159 as CSJ 0215-01-051, MPO project 5392. It covers widening from two lanes to six with a raised median or continuous left-turn lane, and it carries a let year of 2033. The MPO's Mobility 2050 project list, dated April 2024, shows the same segment at a total cost of $72.1 million.

The same document lists the segment at the other end of the current work, from Bulverde Road to Farhills Drive, with a let year of 2033 as well. The six lanes being finished now will have older road at both ends for years.

Here's how the corridor breaks down, from Bulverde toward Vintage Oaks:

Segment of SH 46 What's planned Where it stands Figure on record
Bulverde Road to Farhills Drive Two lanes to six Let year 2033 in AAMPO's 2024 TIP review Not listed in this table
Farhills Drive to Bentwood Drive Two lanes to six, raised medians, center turn lane Under construction by Webber; TxDOT estimates Winter 2026 $59 million
Bentwood Drive to FM 3159 Two lanes to six Let year 2033 in AAMPO's 2024 TIP review $72.1 million
SH 46 at FM 3159 Interchange, or standalone overpass Right of way and environmental clearance done; start expected in five to ten years from January 2026 $39 million

The $39 million and $72.1 million figures cover different work. One is the interchange as described to the county court. The other is the full Bentwood-to-FM 3159 widening in a regional plan, a segment that ends at the same intersection. The public record doesn't say whether the $72.1 million figure includes the overpass, so the two can't simply be added together for a corridor total.

The 2033 let year is the most specific date anywhere in the public record. It also comes from April 2024 planning documents, and planning years can move. It falls inside the five-to-ten-year window Boyd gave in January, which runs from about 2031 to 2036. Letting is when TxDOT awards a construction contract, not when traffic moves onto a finished road. For the widening, the farthest-along plan on file puts the contract award about seven years from now.

What this means for the drive you make every day

Over the next several years, the SH 46 and FM 3159 intersection is likely to look much the way it does now, with improvements arriving to the west first. Once the Farhills-to-Bentwood work is done, the trip toward US 281 and Bulverde should get easier past Bentwood Drive, since the new road has a center turn lane, raised medians and new signals. East of Bentwood, the road stays two lanes until the 2033 segment is built.

The intersection also has a place in the county's broader planning. A My Canyon Lake report from May 2026 on Comal County's draft road plan included "FM 3159 at State Highway 46" among the intersection improvements under consideration. It also listed FM 311 from Canterbury Road to FM 3159 for safety and mobility work. Both were items on a draft list, with no schedule attached, and the county warned that bonds may be needed to pay for future projects.

Signs that the overpass is actually getting close would include:

For closures on a given day, TxDOT points travelers to its live closure map on DriveTexas.

If you're weighing a move into or out of Vintage Oaks and want to know how the SH 46 timeline fits your plans, The Renfeld Group can walk through it with you, including how the commute and the corridor's construction phases come up when buyers compare homes along FM 3159. Request a Custom Market Plan and we'll start from the road you drive every day.